Step 1 Set smoke sensor parameters.
1.
2.
3.
4.
Step 2 Check the monitoring functions of smoke sensor.
Table 8-27 Function check
Check Method
Simulate a
smoky
environment
under the smoke
sensor.
----End

8.7.31 How Can I Set and Add the WLDS900 Water Sensor?

If a water sensor is installed, perform the following steps to configure it.
Prerequisites
One end of the straight-through cable has been connected to the RJ45 port on the
WLDS900 water sensor, and the other end has been connected to the AI/DI port
on the ECC800-Pro.
Context
Procedure
Step 1 Set water sensor parameters.
Issue 04 (2021-10-09)
NO TE
In this example, the smoke sensor is connected to the AI/DI_1 port on the UIM20A
expansion module.
Log in to the ECC800-Pro WebUI as an administrator.
Choose Monitoring > System > UIM Group> UIM n > Running Parameters.
In AI/DI_1 Port Settings area, set AI/DI_1 sensor to Enable, click Submit.
Set AI/DI_1 sensor type to Smoke sensor, click Submit.
Normal Connection Status
Smoke sensor status(AI/
DI_1) is displayed on the
active alarm page of the app
or WebUI.
To use the AI/DI sensor, enable the corresponding AI/DI port and name the
sensor. The specific alarm then can be reported.
If the sensor is prefabricated, only check its settings.
The actual value prevails. Only the method of the parameter settings is
described.
Copyright © Huawei Technologies Co., Ltd.
Alarm Clearance Method
If Smoke sensor type is
Smoke Sensor, power off
and reset the smoke sensor
to clear the alarm.
8 FAQ