9.1 Linkage Control Introduction

The ECC800-Pro provides the linkage control function. You can set logic rules and
control the DO output signal by collecting the signal value.
You can select signals (such as the AI/DI device status signals) and perform logic
operations such as AND, OR, NOT, GREATER THAN, LESS THAN, DELAY, and
FILTER. The operation result can be provided to the dry contact to meet the site
control requirements.
Logic Parameters
The following are the inputs, operators, and outputs for linkage control logic
programs:
Issue 04 (2021-10-09)
Inputs:
Sample: such as AI/DI device signals
Alarm: such as AI/DI alarm signals
Constant
Register: A register can combine multiple levels of logic programs.
Operators:
AND: The output is valid if both inputs are valid.
OR: The output is valid if either input is valid.
NOT: The output is the inverse value of the input signal or constant.
>: The output is active if the input is greater than the constant.
<: The output is active if the input is less than the constant.
DELAY: The output of the input signal or constant is delayed and the
output is constant.
FILTER: The output is active if the input reaches the constant.
Outputs:
Outputs are associated with dry contact outputs and can be used for
generating alarms or controlling devices.
Copyright © Huawei Technologies Co., Ltd.
9

PLC Function

9 PLC Function
391

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ecc800

Table of Contents