Remote Communication; Binary Signal Transfer - Hitachi RET670 Commissioning Manual

Table of Contents

Advertisement

Section 11
Testing functionality by secondary injection
Test of the multiple command function block and multiple transmit is recommended to be performed
in a system, that is, either in a complete delivery system as an acceptance test (FAT/SAT) or as parts
of that system, because the command function blocks are connected in a delivery-specific way
between bays and the station level and transmit.
Command and transmit function blocks included in the operation of different built-in functions must
be tested at the same time as their corresponding functions.
11.17

Remote communication

11.17.1

Binary signal transfer

Prepare the IED for verification of settings as outlined in section
settings".
To perform a test of the binary signal transfer functions, the hardware (LDCM) and binary input and
output signals to transfer must be configured as required by the application.
There are two types of internal self-supervision of the binary signal transfer:
The I/O-circuit board is supervised as an I/O module. For example it generates FAIL if the board
is not inserted. I/O-modules not configured are not supervised.
The communication is supervised and the signal COMFAIL is generated if a communication
error is detected.
Status for inputs and outputs as well as self-supervision status are available from the local HMI under
Self-supervision status: Main menu /Diagnostics /Internal events
Status for inputs and outputs: Main menu /Test /Function status , browse to the function group
of interest.
Remote communication related signals: Main menu /Test /Function status /Communication /
Remote communication
Test the correct functionality by simulating different kind of faults. Also check that sent and received
data is correctly transmitted and read.
A test connection is shown in figure 59. A binary input signal (BI) at End1 is configured to be
transferred through the communication link to End2. At End2 the received signal is configured to
control a binary output (BO). Check at End2 that the BI signal is received and the BO operates.
Repeat the test for all the signals configured to be transmitted over the communication link.
276
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 504 165-UEN Rev. K
"Preparing the IED to verify
Transformer protection RET670
Commissioning manual
SEMOD53601-1 v1
M14951-2 v6