Siemens SICHARGE UC 150 UL Installation And Operation Manual page 37

Plug-in dispenser
Table of Contents

Advertisement

Electrical installation
• Auxiliary voltage:
The SICHARGE UC dispenser is designed for the connection to the low-voltage network (230 VAC) via the
SICHARGE UC charging station. Connect the SICHARGE UC dispenser to the SICHARGE UC charging station
using a properly sized supply line.
• Direct voltage:
The SICHARGE UC dispenser is designed for the connection of direct voltage to a SICHARGE UC charging
station. Connect the SICHARGE UC dispenser using a properly sized cable.
Note
Routing of DC cables to prevent radio interference
The DC charging cables from the SICHARGE UC charging station to the SICHARGE UC dispenser must either be
buried underground or fastened directly to the floor. We recommend using shielded cables for running the
cables above ground to reduce the electromagnetic radiation of the cables. Additional measures may be
necessary, however, in case of interferences of the radio spectrum these include, for example, the use of
EMC filters or ferrites that must then be installed at the output of the DC charging cable.
• Ethernet:
Connect the SICHARGE UC dispenser and the SICHARGE UC charging station with an Ethernet cable.
These are the specifications for cable routing:
– Low-voltage and DC cables must be installed shielded from the Ethernet cable.
– Separate cable routing to low-voltage and DC cables (minimum 20 cm).
– Lay the Ethernet cable close to grounded cabinet components.
– Ethernet cables and low-voltage and DC cables may only cross each other at a 90° angle.
– Ground the shielding of the Ethernet cable at both cable ends.
• Fiber:
– Connect the SICHARGE UC dispenser and the SICHARGE UC charging station with fiber-optic cable.
– Avoid sharp bends in the fiber-optic cable during installation.
Grounding instructions
This unit is to be connected to a grounded, metal, permanent wiring system; or an equipment-grounding
conductor is to be run with circuit conductors and connected to an equipment-grounding terminal or lead
on the SICHARGE UC charging station. Connections to the SICHARGE UC charging station shall comply with
all local codes and ordinances.
Cable routing considerations
All circuits (incoming AC power wiring, DC wiring to dispensers and communications wiring) should be
ran in separate conduit runs until reaching the cable gland plates.
Installation and Operations Manual | SICHARGE UC 150 UL Plug-in Dispenser
37

Advertisement

Table of Contents
loading

Table of Contents