6 Wiring and Connecting

6.4 Connecting the GOT

Connect the display module of GOT2000 series to the DISPLAY I/F connector of the CNC CPU unit using a LAN cable.
Refer to the following manuals for the details on the connection:
"GOT2000 Series Connection Manual (Mitsubishi Products)" SH(NA)-081197ENG-O(1605)MEE
"GOT2000 Series User's Manual (Hardware)" SH(NA)-081194ENG-O(1605)MEE
Use the cable, connector and hub that comply the IEEE802.3 100BASE-TX standard.
Shielded twisted pair cable (STP) is necessary to run a LAN cable out of the control panel. Install a ferrite core (TDK
product, ZCAT3035-1330) around the cable. (Refer to "EMC Installation Guideline: EMC Countermeasure Parts: Ferrite
Core Installation Method" to see how to install the ferrite core.)
Be sure to separate the LAN cable from the drive line, because LAN cables are easily affected by noise.
R16NCCPU
(100BASE-T STP Straight)
or
Cable J303 (100BASE-T STP Straight)
HUB
Cable J303
79
GOT2000
IB-1501452-C