 Two (2) stabilized manifold connectors (compatible with the manifold)
Install the input lines and manifold:
1.
Install the manifold on the XIMV using the manufacturer's
instructions.
2.
Locate the tap valves on the meter run orifice and the corresponding
high and low inputs on the installed manifold.
3.
Measure, cut, and bend the tubing to ease installation of the fittings
into the orifice tap valves and the manifold.
4.
Install the nut and ferrule onto the tubing end.
NOTICE – Equipment damage. To avoid damage to the stainless-
steel tubing, fittings, and valves, always use a backup wrench
to stabilize and eliminate tension on both sides of the
connection when tightening. Damaged connections may
introduce leaks into the system resulting in inaccurate
measurement.
5.
Insert the ferrule into the fitting and slide the nut onto the ferrule
and tighten.
6.
Repeat step 5 for each tubing connection point.
Leak-test the manifold and tap valve connections. See section
test manifold and tubing connections.