Planned maintenance schedule
Perform the planned maintenance procedure every 2 years after installation. Perform the
procedure in the following order:
1.
Visual inspection (section 10.1)
2.
Electrical safety tests (section 10.2)
3.
Functional check (section 10.3, all steps)
Replace the CPU timekeeper battery every 5 years, or whenever the Service Monitor Error
Code 0xHOST1100 message is shown.

10.1 Visual inspection

Follow the procedure in section

10.2 Electrical safety checks

Electrical safety tests provide a method of determining if potential electrical health hazards to
the patient or operator of the device exist.
Perform the following electrical safety tests described in detail in chapter
checkout:
8.2.1. Test setup
8.2.2. Power outlet
8.2.3. Power cord and plug
8.2.4. Ground integrity check
8.2.5. Ground leakage current test
8.2.6. Testing touch current
Record the values of the tests on the Appendix

10.3 Functional check

10.3.1 Start-up

Follow the procedure in section

10.3.2 Display

Follow the procedure in section
10.3.3

PSM / PDM identification

1.
Configure the ECG1 waveform field and the NIBP parameter window to the patient
monitor screen with adequate priority. Connect a PSM or PDM module to the patient
monitor.
2.
Verify that the ECG waveform field, the NIBP parameter window and the related
information appear on the patient monitor screen.
10.3.4

E-module identification

1.
Log in to Webmin.
126
2106778-001
8.1. Visual
inspection.
B. Maintenance check
8.3.1.
Start-up.
8.3.2.
Display.
8. Installation