ABB GOE 2600 Installation And Commissioning Manual page 51

Transformer bushing
Table of Contents

Advertisement

6.
Apply Molykote Multilub to the M10 bolts (6).
7.
Install the M10 bolts (6) and plain washers (7).
8.
Tighten the M10 bolts (6) in a crosswise
sequence.
9.
Tighten the M8 bolts (24) in a crosswise
sequence.
10.
Install the external connection. Refer to the documentation from the supplier of the external
connection.
End of instruction
Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
CAUTION!
Make sure that the outer terminal
moves straight down. Turn each bolt a
little, and then the next bolt, until all
bolts can be tightened to the correct
torque.
Torque
40 ±4 Nm
Torque
20 ±2 Nm
51