ABB GOE 2600 Installation And Commissioning Manual page 16

Transformer bushing
Table of Contents

Advertisement

3.
Remove the support blocks from the transport box and put them on the ground.
4.
Install the lifting tool (88) on the flange.
5.
Attach a soft lifting sling to the lifting tool (88) on
the lower part of the flange and then to the crane
hook.
6.
Attach a soft lifting sling to the top part of the
porcelain insulator.
7.
Carefully lift the bushing.
8.
Make sure that the support blocks are in the same positions as the support blocks in the
transport box.
16
CAUTION!
Make sure that the ground is flat.
CAUTION!
Attach the soft lifting sling as close to
the top housing as possible, or damage
will occur.
Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23