11.
When installing the bushing at site:
1.
Measure the values (X1) and (c).
2.
Record the values in Measurement record,
page 83, for future reference.
Keep the document with the substation
documentation.
End of instruction
48
Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23