5.
Install the tie bolts (86).
6.
Place the lifting tool, top part (1) on the top and
tighten the nuts.
End of instruction
4.3.2 Lifting the bushing for installation on the transformer
Procedure
1.
Make sure that the crane can lift the bushing. Refer to the net weight in the packing list.
2.
Align the second crane hook with the lifting tool, top part on the bushing.
3.
Attach soft lifting slings (8) from the lifting holes,
through the lifting tool, top part to the second
crane hook.
22
NOTE!
The first crane is still attached to the
flange lifting tool (88).
Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23