Figure 3-13 Castors off the floor
Step 2 Check whether the bottom of the cabinet is horizontal by using a level. If the cabinet is not
leveled, adjust the leveling feet.
----End
3.2.2 (Optional) Installing Antiseismic Kits
Procedure
Step 1 Determine the positions for installing the antiseismic kits. Mark mounting holes based on the
drawings, as shown in
Issue 10 (2015-09-15)
Figure
3-14.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Installation