Creating the Drive Project OFFLINE
When the module is ready for operation, the text "OK" appears in the field to the
right of the pushbutton (see Fig. 3-9).
In this case, the station address is displayed along with the additional current
bus parameters and version data.
Fig. 3-9
12.To display the stations, click Read.
When the module is ready for operation, the system generates a list of all the
active stations on the bus.
The symbols for indicating the operating mode of the station have the following
meanings:
– An empty checkbox with a gray background (same background color as the
tab): No partner device found
– Empty checkbox with a light background: Passive station (e.g. DP slave)
– Checkmark on a light background: Active station (e.g. DP master)
– Checkmark on a gray background: Active station ready to be integrated into
the network
Note
This generates considerable load on the bus and may take a few seconds.
13.To complete the process of setting and diagnosing the PC/PG interface, choose
OK, OK and Continue >.
3-38
Read button
Apply
SIMATIC NET diagnostics – CP5511 (PROFIBUS) after the test
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 03/2006 Edition