Fig. 5-12
10.Once the automatic commissioning is complete, click Close.
In the project navigator, all the drive unit components that have been found are
displayed with, for example, the Control Unit, infeed, and drive (see Fig.
5-13).
Fig. 5-13
11. Choose Disconnect from target system.
The drive unit, components, and drives are installed in the STARTER project.
You now just have to configure the drive motors and check the topology.
To do so, proceed as described in Section 5.4.
 Siemens AG 2006 All rights reserved
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 03/2006 Edition
Close automatic commissioning
Choose
Disconnect from target system.
Configuration with, for example,
Control Unit, infeed, and drive.
Automatic configuration
Creating the Drive Project ONLINE
Close