Commissioning

5.2 STARTER commissioning tool

Important information prior to commissioning
The cabinet unit offers a varying number of internal signal interconnections depending on the
delivery condition and the options installed. For the converter control to be able to process
the signals correctly, several software settings must be made.
During initial power-up of the Control Unit and during first commissioning, parameter macros
are executed and the necessary settings made.
The settings are documented in the Appendix.
After initial power-up, first commissioning, and also following a "Parameter reset to factory
settings", individual parameter values deviate from the factory settings stated in the List
Manual.
5.2
STARTER commissioning tool
Description
You can use the STARTER commissioning tool to configure and commission SINAMICS
drives and drive systems. The drive can be configured using the STARTER drive
configuration wizard.
Note
This chapter shows you how to carry out commissioning using STARTER. STARTER
features a comprehensive online help function, which provides detailed explanations of all
the processes and available system settings.
For this reason, this chapter only describes the individual commissioning steps.
Prerequisite: STARTER Version
The following STARTER version is required for commissioning SINAMICS with firmware
V4.5:
● STARTER V4.3
Prerequisites for installing STARTER
Hardware
The following minimum requirements must be complied with:
● PG or PC
● Pentium III, at least 1 GHz, (> 1 GHz recommended)
● 1 GB work memory (2 GB recommended)
● Screen resolution 1024×768 pixels, 16-bit color depth
● Free hard disk space > 3 GB