For this purpose, two grounding harnesses are needed. They can be ordered separately
as an optional grounding harness set (consisting of two grounding harnesses plus a
telescopic insulating pole) for the 3-phase power input.
Notice: To adapt grounding harness ordered from ABB, ball type grounding studs are
provided as option.
3
2
1
1
2
3
Example for grounding harness
1. Open the COU door.
2. Connect the enclosure grounding clamp (item 2 in the figure above) to the cabinet's
PE busbar.
3. Remove the protective plate between COU and TEU.
Telescopic insulating pole
Enclosure ground clamp
Busbar ground clamp