Cables And Pe Busbar Between Integrated Transformer And Drive - ABB ACS580MV Hardware Manual

200 kw to 6300 kw, 6 kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

Cables and PE busbar between integrated transformer
and drive
2
1
Transformer unit
2
Drive unit
3
Control cable lead-through
4
PE busbar
Drive with integrated transformer
Cables and PE busbar between drive and integrated transformer includes the following
connections:
Transformer primary and secondary cables
Temperature sensor cables
Three-phase power supply cable to each of the transformer fan units
PE Busbar to connect INU and TRU.
or
Auxiliary supply from internal main transformer (option)
Heating cable (option)
The cables are identified by their specific number and are labeled with the designation of
the terminal where they are connected to.
The terminals for the primary and the secondary cables are located on the side wall of the
drive cabinet. The transformer terminals are accessible through the left side door of the
transformer unit. The cables must be mounted to the transformer terminals as shown in the
figure below.
1
 
4
Electrical installation 69
3

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents