60 Mechanical installation

Necessary tools

The tools required for moving the unit to its final position, fastening it to the floor and wall
and tightening the connections are listed below:
crane, fork-lift (check load capacity!), iron bar, jack and rollers
Pozidrive and Torx (2.5...6 mm) screwdrivers
torque wrench
set of wrenches or sockets

Overview on installation work

The installation includes the following work:

Preparing the foundation

Moving the converter and transformer units to their final location
Aligning and bolting together the units
Fixing base frames to the floor

General notes on installation

Foreign matter and particularly metallic dust can cause failure and damage when the drive
is energized.
Ensure that foreign matter cannot enter the cabinet:
Close the doors and cover openings completely when work is discontinued.
Retrieve any foreign matter which accidentally dropped into the cabinet.

Dimensions, clearances

See Outline drawing for information on:
Cabinet dimensions
Clearances to be observed
Mounting hole sizes
Preparing the foundation
The floor must be of non-flammable material, with a smooth and non-abrasive surface,
protected against humidity diffusion, leveled and able to support the weight of the cabinet.
The maximum recommended allowable overall unevenness is  5 mm per 5 m.

Cable ducts

Cable ducts should be of non-flammable material with a non-abrasive surface.
All cable entries and exits should be protected to prevent dust, humidity and animals
entering the drive.

Fire protection

Suitable fire protection measures should be applied to prevent fire spreading into the drive.