Mounting

1. Install the new module in reverse order of removal.
2. Switch on all miniature circuit breakers in the control compartment.
3. When the work is completed the drive can be started up again. See Chapter
Operation, Energizing and starting the

Converter module testing and repair

Testing and repair of a defective power module is done at ABB works. Send the module in
for repair.

Replacing the power module fuse R4 - R6

1. Stop, de-energize and ground the drive following the steps in section
the drive for maintenance
2. Switch off all miniature circuit breakers in the control compartment.
3. Ground the power modules according to
hook
on page 107.
4. Loosen the 2 mounting screws of the fuse to be replaced.
5. Pull out the fuse.
6. Install the replacement fuse in reverse order of removal.
7. Reinstall the power module in reverse order of removal.
8. Switch on all miniature circuit breakers in the control compartment.
9. When the work is completed the drive can be started up again. See Chapter
Operation, Energizing and starting the
Replacing power module fuse on a module of frame size R4 - R6
drive.
before you start the work.
Grounding power module with grounding
drive.
Maintenance 123
Shutting down

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents