Constructional data of the foundation

The panels can be bolted or welded to the foundation rails. Fasten each panel diagonally to
the foundation rails at two points at least. Use M10 fixing bolts as a minimum.
Tightening torque: 60 Nm.
Damage to the welded seams
Welded seams are susceptible to corrosion.
➭ After welding, protect the welded seams professionally against corrosion.
Fig. 24:
Overview of floor openings and fixing points
Base frame
Floor opening for high-voltage cables
Switchgear termination
Foundation rails
For large panel connection housings, the dimension must not be smaller than 1145 mm
1)
Bolt the standard design diagonally to the foundation rails at 2 points
(use sheet EN 10021, 4x40x60 mm).
Fig. 25:
Bolted joints of standard design
Fixing points (26x45 mm) for M10
Bolt the aseismic design to the foundation rails at all 4 points using a floor fixing profile.
The floor fixing profile is included in the scope of supply. The fixing material is not included in
the scope of supply. (Part number: 865-2944.0 without fixing material).
Bolted joints of the aseismic design
Fixing points (26x45 mm) for M10
Fixing profile
NOTICE
Fixing holes (26x45) for M10
Area for floor openings for control cables
Operating side of the panel
Fixing profile
Installation