Ekip Synchrocheck - ABB SACE Emax 2 Series Operating Instructions Manual

Low voltage air circuit-breaker
Table of Contents

Advertisement

12 - Ekip Synchrocheck

Additional functions Certain options can be remotely configured in the synchronism conditions described above:
247 | © 2023 ABB | 1SDH001330R1002 - ECN000297030
Ekip Synchrocheck is an accessory module that is used to control closing of an actuator when synchronism
conditions, programmable by the user, exist.
To actuate synchronism:
• Ekip Synchrocheck and the internal sockets measure, respectively, the voltage on the external
contacts (external voltage) and on the internal contacts (internal voltage) of the actuator
• Ekip Synchrocheck manages a closing contact
NOTES:
• the actuator is described as a circuit-breaker in the following description and in the menus
• with a generator and the actuator being configured: Normally, the external voltage is that of
the grid and the internal voltage is that of the generator
IMPORTANT: only one Ekip Synchrocheck can be installed on each CB
Mode The module operates in two modes, configurable by the user (manual-mode configuration) or managed
automatically by the unit (automatic-mode configuration).
Conditions
Busbar active
Dead busbar and
configuration:
Normal
NOTE: with dead busbar and configuration: Reversed, the roles of the internal and external
voltages are reversed
Synchronism signal:
• is activated and maintained, after synchronism has been reached, for at least 0.2 s
• is deactivated when synchronism ends or the circuit-breaker is opened (with condition: Evaluate
CB status = enabled) or communication with Ekip Touch is interrupted
• the open circuit-breaker condition can be added (disabled by default)
• removal of the frequency and phase controls can be disabled
IMPORTANT: to be able to disable the frequency and phase controls, first make sure that
the required frequency and phase correspondence between external and internal contacts
already exists
Description
Operation with external voltage other than zero:
• synchronism search starts if the external voltage is (0.5 Un by default) or
more, for at least (1 s by default)
• synchronism is considered to have been reached if the differences between
RMS values and frequencies and the voltage phases are (0.12 Un, 0.1 Hz, and
50° by default) or less
Operation with one of the voltages nil:
• synchronism search starts if the internal voltage is (0.5 Un by default) or
more, for at least (1 s by default)
• synchronism is considered to have been reached if the external voltage is (0.2
Un by default) or less, for at least (1 s by default)
ABB | SACE Emax 2
External electronic accessories
12 - Ekip Synchrocheck