Procedure - ABB i-bus KNX Product Manual

Dali gateway emergency lighting
Hide thumbs Also See for i-bus KNX:
Table of Contents

Advertisement

®
ABB i-bus
KNX
Commissioning
3.1.1.1

Procedure

Insert the required device into the project
Import the current application program into the ETS.
Perform parameterization and program the device.
After you have programmed a device, you can transfer the settings to a second device.
Right click on the product and select Plug-in > Convert in the context menu for this purpose.
Thereafter undertake the required settings in the Convert dialog.
Finally, exchange the physical address and delete the old
device.
DGN/S 1.16.1 | 2CDC 507 114 D0201 25