Electrical installation
4.5 Connections
Cable routing of signal cables to SMC10/20/30 Sensor Module
1. Feed the cable for the customer terminal block into the cabinet from the bottom left.
2. Remove approx. 3 cm of the insulation at the level of the shield plate in the lower part of
3. To secure the cable in accordance with EMC requirements, snap the clip onto the shield
4. Use cable ties to secure the cable at suitable points.
5. Guide the cable further up into the cabinet and, when it reaches the SMC10/20/30
6. Use cable ties to secure the cable at suitable points.
7. Connect the cable to the SMC10/20/30 Sensor Module (-B81/-B82/-B83).
98
Frame size:
FX+GX
HX+JX
the cabinet and attach the cable.
plate.
Sensor Module (-B81/-B82/-B83), guide it to the right to the Sensor Module. When
doing so, route the cable in a similar manner to the standard cables that have already
been installed in the cabinet.
(→ See the chapter titled "Options", K46, K48 and K50 (Sensor Module Cabinet-
Mounted SMC 10, 20 and 30)
S120 Cabinet Modules Equipment Manual
Manual, (GH5), 10/2008, A5E00427098A

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics s120 cabinet module

Table of Contents