7.6
First commissioning of the PLC completed
First commissioning of the PLC completed
You have completed the first commissioning of the PLC.
The PLC and NCK are in the following state:
● LED RUN illuminates GREEN continuously.
● Status display shows a "6" with a flashing point.
Continue with the steps for commissioning the SINAMICS drives.
You can access the HMI as follows:
Figure 7-18
IBN CNC: NCK, PLC, drive
Commissioning Manual, 07/2007, 6FC5397-2AP10-3BA0
⇒ PLC and NCK are in cyclic operation.
PLC commissioning complete
7.6 First commissioning of the PLC completed
PLC commissioning
59