6.8 Cooling Capacity Management

6.8.1 Setting Cooling Management Parameters

Prerequisites
Context
Procedure
Step 1 Log in to the ECC800 WebUI as an administrator.
Step 2 Choose Monitoring > Cooling > Running Parameters to access the Temperature and
Humidity Parameters page. Check whether Temperature and humidity control type is
Cold-aisle.
Step 3 Choose Monitoring > Cooling > Running Parameters to access the Running Parameters
page. Set Number of redundant smart cooling products and Local yearly highest
temperature as required and tap Submit.
Issue 05 (2019-09-16)
Specifications
SPD
Main switch
All smart cooling products communicate with the ECC800 properly.
The electricity management configuration is complete, and the IT cabinet power
statistics are normal.
The number of smart cooling products (number of started smart cooling products) with
the valid maximum cooling capacity received by the ECC800 is greater than or equal to
the Number of running air conditioners in this group in Teamwork settings of smart
cooling products.
Only for water cooled smart cooling product.
After the smart cooling product is successfully connected to the ECC800, the cooling
capacity management function is enabled by default.
The cooling capacity of the chilled water smart cooling products in the smart module can
be managed by collecting the running parameters of the chilled water smart cooling
products and using the smart module electricity management function.
Copyright © Huawei Technologies Co., Ltd.