3. Click "Assume control priority". The "Assume Control Priority" dialog box is opened.
Note
If you are using an infeed without a DRIVE‑CLiQ interface, you will have to interconnect
the "Infeed operation" signal (drive parameter p0864) yourself. If you are using an infeed
with a DRIVE‑CLiQ interface, select the infeed for which the control priority is to be assumed
under "Infeed" in the "Assume Control Priority" dialog box.
If the infeed signal "Closed-loop control operation" already has a BICO interconnection to
the drive, the infeed is permanently specified (infeed selection and checkbox are grayed
out).
The infeed must be switched on before the drive can move ("LM" button, switch infeed on/
off).
Figure 7-44
4. Read the notes and confirm these with "Accept."
5. Activate the "Enables" checkbox to enable the drive.
All enables are now set with the exception of ON/OFF1.
SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
Assume_control_priority
Commissioning (software)
7.6 Testing a drive with the drive control panel
255

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotion cx32-2Simotion cbe30-2Simotion tb30

Table of Contents