Configuration Of The Et 200Sp/Mp Timer Didq - Siemens SIMOTION D4x5-2 Commissioning And Hardware Installation Manual

Hide thumbs Also See for SIMOTION D4x5-2:
Table of Contents

Advertisement

See also Section Configuration of the D4x5-2 I/Os (terminal X122/X132) (Page 284)
Note
If symbolic assignment is activated retrospectively for a project in which message frames have
already been configured and interconnected, these can be changed together with the BICO
interconnections.
For this reason, make a backup copy of your project before activating the symbolic assignment.
TB30, TM15 DI/DO and TM31 are especially affected.
See also Section Symbolic assignment / adaptation (Page 169)
7.12.1.4

Configuration of the ET 200SP/MP timer DIDQ

The I/O terminals of the ET 200SP and ET 200MP timer DIDQ can be used as drive-related I/
Os for measuring input and output cam applications.
The DI/DQ timers are configured via the hardware configuration of STEP 7 or TIA Portal. The
properties of the I/O channel can be configured in the parameterization dialog box, for example
● Timer DI for use of the I/O as measuring input input or
● Timer DQ for use of the I/O as cam output
Note
For the technological use of the timer DIDQ, you must operate the I/O station isochronously
on PROFINET:
● ET 200SP timer DIDQ: With SCOUT or SCOUT TIA, IM 155-6 PN HF required
● ET 200MP timer DIDQ: Only with SCOUT TIA, IM 155-5 PN ST or HF required
Operation via PROFIBUS is not possible.
For detailed information on the configuration, see
SIMOTION SCOUT and SIMOTION SCOUT TIA Commissioning Manual
SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
7.12 Configuring drive-related I/Os (with symbolic assignment)
Technology Modules TM Timer DIDQ for
Commissioning (software)
287

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotion cx32-2Simotion cbe30-2Simotion tb30

Table of Contents