7.4.5.1

Loading a project created offline to the target system

Requirement
● Your project, including all SINAMICS Integrated and CX32‑2 drive components, must have
been configured already (see Preparing for configuration (Page 212)).
● The actual topology must correspond with the reference topology.
Note
A step-by-step commissioning with the CX32-2 controller extension is described below.
In a step-by-step procedure, first the D4x5-2, then the SINAMICS Integrated and finally
each CX32‑2 is commissioned. This step-by-step procedure is not mandatory, but has the
advantage that the location and cause of an error are easier to identify.
Procedure
1. Deselect all target devices, with the exception of the SIMOTION D4x5‑2, using the "Target
system" > "Select target devices" menu command in SCOUT.
2. Go online with the D4x5‑2 by clicking "Connect to selected target devices".
3. Select the D4x5‑2 in the project tree. Load the configuration to the SIMOTION D4x5‑2 with
"Download CPU / drive unit to target device".
4. Copy the configuration from RAM to ROM with "Copy RAM to ROM".
5. Select "Connect target device" in the SINAMICS Integrated context menu. You will then be
connected to the SINAMICS Integrated online.
6. Load the parameterization by selecting "Target device" > "Download" in the SINAMICS
Integrated context menu.
7. Copy the parameterization from RAM to ROM with "Copy RAM to ROM".
8. Then select "Load CPU / drive unit to PG" to load the parameterization from the SINAMICS
Integrated back to the programming device in order to back up the SINAMICS parameter
calculations.
The SINAMICS Integrated is now ready for operation (RDY LED flashes green at 0.5 Hz). The
CX32‑2 can be accessed online, although it has not been configured yet (RDY LED flashes
green at 0.5 Hz, DP LED is off).
1. Select "Connect online" in the CX32‑2 context menu. You will then be connected to the
CX32‑2 online.
2. Load the parameterization to the CX32‑2 and copy the parameterization from RAM to ROM.
3. Then load the parameterization from the CX32‑2 back to the programming device in order
to back up the SINAMICS parameter calculations.
SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
Commissioning (software)
7.4 Configuring a CX32-2
217

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotion cx32-2Simotion cbe30-2Simotion tb30

Table of Contents