FusionModule2000 Smart Modular Data Center
Maintenance Guide
Preparations
Procedure
Step 1 Disconnect the upstream fuse for the FusionModule Actuator.
Step 2 Open the cover on the front panel of the FusionModule Actuator, and disconnect
the cables.
Step 3 Label each cable based on the corresponding ports on the FusionModule Actuator.
Step 4 Remove the old FusionModule Actuator from the guide rail.
Figure 5-52 Replacing a FusionModule Actuator
Step 5 Install the new FusionModule Actuator in the original position and connect the
cables.
Step 6 Connect the upstream fuse for the FusionModule Actuator to complete the
networking settings for the new component.
Step 7 Synchronize parameters of the FusionModule Actuator on the ECC800-Pro WebUI.
Step 8 On the ECC800-Pro WebUI, choose System Settings > Device Management >
Device Deletion and select a device type from the Select a device type drop-
down list. Select a desired device in the Devices list, click Delete, and add the new
device to the smart module view.
Step 9 Log in to the ECC800-Pro WebUI, and edit the plan view by adding the new device.
Step 10 Check the parameters and communication status of the FusionModule Actuator to
ensure normal communication.
Step 11 Turn on and then turn off the lights to check that the FusionModule Actuator
supplies power to the lights properly.
----End
Issue 02 (2022-07-30)
Tools: insulation gloves, Phillips screwdriver, step ladder, label, marker
Material: FusionModule Actuator
Copyright © Huawei Digital Power Technologies Co., Ltd.