Monthly Maintenance - Huawei FusionModule2000 Maintenance Manual

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Maintenance Guide

3.3 Monthly Maintenance

Table 3-2 Monthly maintenance for the power supply and distribution system
Item
UPS power grid
environment
Three-phase
power indicators
Surge protection
module
Liquid crystal
display (LCD)
screen on the PDF
Power supply to
devices
Issue 02 (2022-07-30)
Method
Check the
running status
on the UPS
LCD.
Check the
luminance of
the indicators.
Check the
surge
protection
module
indicator and
miniature
circuit breaker
(MCB) status.
Touch the LCD
screen with
your finger.
Check
whether the
switches of
each IT
cabinet are
ON.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Expected Result
● Input voltage:
380 V AC/400 V
AC/415 V AC
(line voltage)
● Output voltage:
380 V AC, 400 V
AC, or 415 V AC
(tolerance: ±1%,
line voltage)
The three-phase
power indicators are
bright.
● The surge
protection
module indicator
is steady green.
● The MCB is ON.
The LCD screen
panel displays
information
properly.
The power supply to
devices is normal.
3 Routine Maintenance
Troubleshooting
● If the input
voltage is
abnormal, check
the power grid
and input cable
connection.
● If the output
voltage is
abnormal, check
the UPS running
status and check
whether an
alarm is
generated.
Replace the
indicator that
generates no or dim
light.
● Replace the
surge protection
module if its
indicator is red.
● If the MCB is
OFF, switch it on.
Check that the
power cable is
properly connected.
Check whether
cables are damaged
or loose.
27

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r022c10

Table of Contents