Making the STARTER settings for PROFIBUS
The following settings are required in the STARTER commissioning tool for communication
via PROFIBUS:
1. Call the menu "Tools > Set PG/PC interface ...".
2. If the interface has still not been installed, click on the "Select" button.
3. In the selection list on the left-hand side, select the module that you want to use as the
interface.
4. Click the "Install" button.
The selected module is then listed in the "Installed" list.
5. Click on "Close".
6. Call the menu "Tools > Set PG/PC interface ..." and click on the "Properties" button.
7. Activate or deactivate the option "PG/PC is the only master on the bus".
Note
PROFIBUS setting
• Baud rate
– Connect STARTER to an operational PROFIBUS:
– Connect STARTER for commissioning:
• PROFIBUS addresses:
The PROFIBUS addresses for the individual drive units must be specified in the project
and must match the address settings on the devices.
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
The STARTER commissioning tool automatically detects the baud rate used by
SINAMICS for PROFIBUS, and this is then used.
The Control Unit automatically detects the baud rate set in the STARTER
commissioning tool, and this is then used.