4.4

Diagnostics of uncommissioned axes

To be able to identify uncommissioned drive objects of the classes "Infeeds", "Motor
Module", "SERVO" and "VECTOR", there is an operating display in parameter r0002.
● r0002 "Infeed operating display" = 35: Carry out the first startup
● r0002 "Drive operating display" = 35: Carry out the first startup
The parameter r0002 "drive operating display" = 35 is then displayed if p3998[D]=0 is in any
data set. Parameter p3998 specifies whether the first commissioning of the drive is still to be
carried out (0 = yes, 2 = no).
Parameter p3998 is set to the value 2 when the calculation of the motor and control
parameters for all data sets has been completed without errors (see r3925 bit0 = 1) and the
encoder selection p0400 is not at 10100 (encoder identification).
The limitation that all drive data sets (DDS) must be commissioned in order to exit
commissioning is ensured by checking the parameters involved (see also F07080 in the
SINAMICS S120/S150 List Manual).
Infeed Module
An infeed (Active Line Modules, Basic Line Modules or Smart Line Modules with DRIVE-
CLiQ) is considered commissioned when the line voltage and line frequency have been
parameterized with appropriate values. A basic setting of 50 Hz or 60 Hz is expected for the
line frequency.
The line voltage p0210 may need to be adjusted to the existing power supply.
To exit the state r0002 "Infeed operating display" = 35, set parameter p3900 "completion of
quick commissioning" to the value 3, after any necessary adjustment to the line voltage.
For a 400 V unit, for example, the voltage p0210 is always initialized with 400 V. Although it
is possible to switch on when connected to all line supplies from 380 V to 480 V, operation is
not always optimal and/or alarm messages are displayed (see SINAMICS S120/S150 List
Manual).
If the unit is not connected to a 400 V line supply, then the rated voltage p0210 should be
adjusted. This can also be done after the first time the unit is switched on, by setting
p0010 = 1.
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
4.4 Diagnostics of uncommissioned axes
Diagnostics
363

Advertisement

Table of Contents
loading

Table of Contents