First commissioning control mode vector U/f in booksize format

The example provided in this section explains all the configuration and parameter settings,
as well as the tests that are required for initial commissioning. Commissioning is carried out
using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met according to Section 1.1.
2. The check list - Table 1-1 or 1-2 from the Chapter Preparing for commissioning - has
3. The STARTER commissioning tool is installed and activated.
4. The power supply (24 V DC) is switched on.
2.6.1

Task

A drive, booksize format with vector U/f control mode with the following components is to be
commissioned for the first time:
Table 2- 10
Designation
Closed-loop control and infeed
Control Unit
Smart Line Module
Line filter package 10 kW
Drive 1
Motor Module
Motor
Drive 2
Motor Module
Motor
The enable signals for the infeed and the drive should be realized via terminals.
Commissioning Manual
Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
been filled out and the points complied with.
--> see the "Readme" file on the STARTER installation CD.
Component overview
2.6 First commissioning control mode vector U/f in booksize format
Component
Control Unit 320-2DP
Smart Line Module 10 kW
Line filter and line reactor
Single Motor Module 5 A
Induction motor
Single Motor Module 5 A
Induction motor
Commissioning
Order number
6SL3040-1MA00-0AA0
6SL3130-6AE21-0AAx
6SL3130-0GE21-0AAx
6SL3120-1TE15-0AAx
1LA
6SL3120-1TE15-0AAx
1LA
89

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents