Commissioning
2.5 First commissioning, servo control mode, booksize format
What to do?
4.
Summary
5.
Configure the drive
unit.
2.5
First commissioning, servo control mode, booksize format
The example provided in this section explains all the configuration and parameter settings,
as well as the tests that are required for initial commissioning. Commissioning is carried out
using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met according to Section 1.1.
2. The check list - Table 1-1 or 1-2 from the Chapter Preparing for commissioning - has
3. The STARTER commissioning tool is installed and activated.
4. The power supply (24 V DC) is switched on.
82
You have now created the project.
-> Click "Complete".
Once you have created the project, you have to configure the drive unit. The following
sections provide some examples.
been filled out and the points complied with.
--> see the "Readme" file on the STARTER installation CD.
How to do it?
Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
Commissioning Manual