First Commissioning With The Aop30 - Siemens SINAMICS G150 Operating Instructions Manual

Converter cabinet units 1750 kw 2700 kw
Hide thumbs Also See for SINAMICS G150:
Table of Contents

Advertisement

5.5

First commissioning with the AOP30

5.5.1
Initial ramp-up
Start screen
When the system is switched on for the first time, the Control Unit is initialized automatically.
The following screen is displayed:
Figure 5-38
When the system boots up, the parameter descriptions are loaded into the operating field
from the CompactFlash card.
Figure 5-39
Converter cabinet units
Operating Instructions, 07/2016, A5E03347396A
Initial screen
Load the parameter descriptions while booting up the system
5.5 First commissioning with the AOP30
Commissioning
241