Requirements On The Levelness Of The Floor - Siemens SINAMICS G150 Operating Instructions Manual

Converter cabinet units 1750 kw 2700 kw
Hide thumbs Also See for SINAMICS G150:
Table of Contents

Advertisement

cabinet doors and also in front of the optional canopies. Option M54 offers additional
protection against water sprayed against the housing from any direction and corresponds to
degree of protection IP54.
The permissible values for climatic ambient conditions must be taken into account.
At temperatures > 40 °C (104 °F) or altitudes > 2000 m, derating is required.
The basic version of the cabinet units complies with the IP20 degree of protection in
accordance with EN 60529.
Installation is realized in accordance with the dimension drawings supplied. The clearance
between the top of the cabinet and the ceiling is also specified in the dimension drawings.
The cooling air for the power unit is drawn in from the front through the ventilation grills in the
lower part of the cabinet doors. The hot air is discharged through the perforated top cover or
the ventilation grilles in the top cover (with option M13/M23/M43/M54/M78). Cooling air can
also be supplied from below through intermediate floors, air ducts, etc. To allow this,
openings must be made in the 3-section bottom panel or individual bottom panels must be
removed.
According to EN 61800-3, the cabinet units are not intended for use in low-voltage public line
supplies that supply residential buildings. High-frequency interference can be expected if it is
used in this type of line supply.
Additional measures (e.g. line filter, option L00) can be fitted for use in the first environment
according to EN 61800-3 Category C2.
Note
Radio service interference due to high frequency (radio frequency) disturbances
The converter can cause high frequency disturbances, which may make interference
suppression measures necessary.
This device is not designed for general use in the first environment (residential area) and
must not be used there without appropriate radio interference suppression measures.
• Have the installation and commissioning with appropriate radio interference suppression
measures preformed by qualified personnel.
3.3.2.2

Requirements on the levelness of the floor

The foundation at the installation location must be horizontal and level, to ensure proper
functioning of the cabinet units.
● Care must be taken to ensure that the doors can be opened and closed and that the
locking systems work properly.
● Flat sections (such as doors, side panels and canopies) must be sealed correctly to
ensure compliance with the specified degree of protection.
● When cabinets are connected (e.g. transport units), air must be prevented from entering
through the gaps.
Converter cabinet units
Operating Instructions, 07/2016, A5E03347396A
Mechanical installation
3.3 Mounting
43