Section 11
Testing functionality by secondary injection
1.
Simulate normal operating conditions with the three-phase currents in phase with their
corresponding phase voltages and with all of them equal to their rated values.
2.
Change the voltages and currents in all three phases simultaneously.
The voltage change must be higher than the set value
be lower than the set value
3.
Apply normal conditions as in step 1.
The BLKU, BLKZ and 3PH signals should reset, if activated, see step
4.
Change the voltages and currents in all three phases simultaneously.
The voltage change must be higher than the set value
be higher than the set value
The BLKU, BLKZ and 3PH signals should not appear.
5.
Repeat step 2.
6.
Connect the nominal voltages in all three phases and feed a current below the operate
level in all three phases.
7.
Keep the current constant. Disconnect the voltage in all three phases simultaneously.
The BLKU, BLKZ and 3PH signals should not appear.
8.
Change the magnitude of the voltage and current for phase 1 to a value higher than the
set value
9.
Check that the start output signals STDUL1 and STDIL1 and the general start signals
STDU or STDI are activated.
10.
Check that the start output signals for the current and voltage phases 2 and 3 are
activated by changing the magnitude of the voltage and current for phases 2 and 3.
11.8.2.6

Completing the test

continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
11.8.3

Fuse failure supervision VDSPVC

Prepare the IED for verification of settings as outlined in section
section
Checking the operation of binary input and output
1.
Simulate normal operation conditions with three-phase voltage on the main fuse group
and the pilot fuse group. Ensure the values are equal to their rated values.
2.
Disconnect one of the phase voltage from the main fuse group or the pilot fuse group.
Observe the binary outputs of the IED. The MAINFUF or the PILOTFUF signals are
simultaneously activated. Only the output circuit related to the open phase will be active
i.e either MAINFUF or PILOTFUF.
3.
Establish a normal voltage operating condition and observe the corresponding output
signals. MAINFUF or PILOTFUF should change to
4.
Set normal conditions as mentioned in step 1.
5.
Enable the BLOCK binary input and repeat step 2. MAINFUF or PILOTFUF should not
appear.
138
The BLKU and BLKZ signals appear without any time delay. The BLKZ signal will be
activated only if the internal deadline detection is not activated at the same time.
3PH should appear after 5 seconds, if the remaining voltage levels are lower than
UDLD< of the dead line detection function.
the set
DU> and DI< .
"Preparing for test"
in this chapter.
© Copyright 2017 ABB. All rights reserved
DI< .
DI< .
0 in about 27 ms.
1MRK 511 403-UEN E
DU> and the current change must
1
and 2.
DU> and the current change must
TESTMODE setting to Off .
GUID-DCCD4C4A-8335-43BA-A2B2-9994380985B0 v2
"Requirements"
and
GUID-004BFFE4-B1C1-4C0E-8D7A-ABE7B566AB28 v2
Bay control REC670
Commissioning manual
M1405-130 v5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rec670

Table of Contents