NetCol5000-A050 In-row Air Cooled Smart Cooling
Product
User Manual
Figure 4-11 Top view of compact installation if the quantity is > 6 (NetCol500-
A120)
Concrete Platform Requirements
The required concrete platform dimensions are different when the concrete
platform is installed horizontally and vertically. The construction requirements are
as follows:
Concrete Platform Requirements for Horizontal Installation
For details about how to make concrete platforms to horizontally install an
outdoor unit, see
Issue 08 (2021-09-17)
NO TE
If necessary, you can use a base to increase the height for compact installation, the
dimensions of the raised base can be obtained based on the BOM code. Take the
NetCol500-A120 as an example.
● When the quantity is 6 or less, if the wall height is 0 mm, the base height is 0 mm. If
the wall height is 1000 mm or lower, the base height is 500 mm or higher.
● When the quantity is more than 6, if the wall height is 0 mm, the base height is 500
mm or higher. If the wall height is 1000 mm or lower, the base height is 1000 mm or
higher.
The concrete platforms are installed horizontally or with a slope of 5 degrees
at most.
Water can drain away after heavy rainfall.
The strength of the concrete platform must be at least C20.
Figure
4-12.
Copyright © Huawei Technologies Co., Ltd.
4 Installation
41