Procedure
Step 1 Log in to the ECC800-Pro WebUI as user admin. Choose Monitoring > Cooling >
FusionCol5000-A0031. The page for commissioning smart cooling products is
displayed.
Step 2 Choose Controls > Control Information, set Power on/off to ON, and click
Submit.
----End
Exception Handling
Step 1 Check that the T/H control mode and T/H set point are properly set.
Step 2 Check that the current time is correctly set.
Step 3 Check that the return air filter is installed in the correct direction.
----End

5.3 Management System Power-On Commissioning

5.3.1 Preparations and WebUI Login

Prerequisites
Procedure
Step 1 Connect a network cable between the PC network port and the WAN1 port
(protected by a security mechanism) on the ECC800-Pro.
Table 5-3 Default IP addresses for the WAN and LAN ports on the ECC800-Pro
Port
WAN1
WAN2
LAN1 and LAN2
Issue 02 (2021-06-30)
NO TE
If no manual operation is performed within 25 seconds after you click On, the equipment
will automatically run according to the preset logic, and the compressor and indoor and
outdoor fans will also run according to environment requirements.
Supported operating system: Windows 7 and later versions
It is recommended that the screen resolution be 1366 x 768 or higher.
Browser: Chrome, Firefox 32, Internet Explorer 11 or later
Copyright © Huawei Technologies Co., Ltd.
Default IP Address
192.168.8.10
192.168.0.10
192.168.248.10 (FusionModule800)
192.168.248.10
5 Power-On Commissioning
109

Advertisement

Table of Contents
loading

Table of Contents