Figure 8-15 Securing the IBBS200D on the base
(1) M12x30 bolt
----End
(Optional) Installing Two Cabinets in Stack Mode
This section describes the procedure and precautions to be taken for installing two cabinets in
stack mode. After a cabinet is installed on a base, another cabinet can be stacked on this cabinet
based on actual requirements.
Procedure
Step 1 Remove the cover plates for cable holes from the top of the lower cabinet, as shown in
8-16.
Figure 8-16 Removing the cover plates for cable holes