Huawei DBS3900 Installation Manual page 433

Hide thumbs Also See for DBS3900:
Table of Contents

Advertisement

DBS3900 (Ver.B)
Installation Guide
Prerequisite
Before soldering the connectors to the E1/T1 cable, ensure that both ends of the E1 cable are
disconnected from any devices. In addition, all the connectors are soldered to the E1 cable during
the same session.
Procedure
Step 1 Link the DB26 male connector of the E1/T1 cable to the port labeled E1/T1 on the UTRP,
GTMU, or WMPT, as shown in
Figure 12-15
Step 2 Route the cables by referring to
the cables.
Step 3 Label the installed cables by referring to Attaching an L-Shaped Label.
----End
Installing a FE/GE Cable
A FE/GE cable transmits baseband signals between a BBU and external transmission equipment
when a DBS3900 is deployed indoors.
Procedure
Step 1 Connect one end of a FE/GE cable to the port labeled FE0 on the GTMU or WMPT in a BBU,
as shown in
Issue 06 (2011-09-15)
WARNING
Figure
12-16.
NOTE
You must use a shielded straight-through FE/GE cable.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
12 Indoor Scenario with DC Power Supply (BBU Installed in
Figure
12-15.
12.4.1 Cabling
Requirements, and then use cable ties to bind
a 19-Inch Rack)