Huawei DBS3900 Installation Manual page 421

Hide thumbs Also See for DBS3900:
Table of Contents

Advertisement

DBS3900 (Ver.B)
Installation Guide
Context
The WGRU is optional, which provides the location function for a base station. For details, see
WGRU.
Procedure
Step 1 Slide a WGRU along the guide rails into a rack, and then tighten four M6x16 screws on the
panel until the tightening torque reaches 3 N·m, as shown in
Figure 12-6 Installing a WGRU
(1) Front panel of a WGRU
l A minimum of 25 mm space on the left and right of a WGRU must be provided for ventilation.
l A minimum of 70 mm and 800 mm space must be respectively provided in the front and at the back of the
Step 2 Install a WGRU PGND cable.
1.
2.
3.
Issue 06 (2011-09-15)
NOTE
WGRU for cabling or maintenance.
Cut the cable to the required length based on the actual cable route.
Add an OT terminal to each end of the cable. For details, see Assembling the OT Terminal
and the Power Cable.
Link the OT terminal at one end of the WGRU PGND cable to the ground bolt on the back
panel of the WGRU, and then link the OT terminal at the other end to external ground bar,
as shown in
Figure
12-7.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
12 Indoor Scenario with DC Power Supply (BBU Installed in
(2) Back panel of a WGRU
a 19-Inch Rack)
Figure
12-6.
408