Creating An Mbts Commissioning Task (Deploying A Gbts When The Nodeb Is Normal) - Huawei 3900 Series Commissioning Manual

Multi-mode base station
Hide thumbs Also See for 3900 Series:
Table of Contents

Advertisement

4 Commissioning the MBTS in GU Mode on the M2000
1.
2.
3.
Step 5 In MBTS List, select an MBTS to be commissioned, and then click
M2000 starts commissioning the MBTS automatically.
l
l
----End
Postrequisite
During the commissioning, you can monitor the MBTS commissioning status through the
M2000 to handle commissioning exceptions in time and ensure that the commissioning can be
performed successfully. For details, see
Commissioning
4.3.3 Creating an MBTS Commissioning Task (Deploying a GBTS
When the NodeB Is Normal)
This section describes how to create an MBTS commissioning task when the NodeB is normal
and you need to deploy a GBTS. After making MBTS commissioning preparations, you can
create an MBTS commissioning task on the M2000 and enable the M2000 to commission the
MBTS automatically.
Prerequisite
l
l
l
Context
The M2000 can commission a maximum of 500 base stations at a time, where one MBTS is
equal to two base stations (the NodeB and the GBTS are not differentiated).
Procedure
Step 1 Choose Configuration > Auto Deployment > MBTS Auto Deployment. The MBTS Auto
Deployment window is displayed.
Step 2 Keep ready the NodeB deployment list.
4-10
Right-click a record in the NodeB List area, and then choose Upload versions and config
files from the shortcut menu. The Upload versions and config files dialog box is displayed.
Select the file to be uploaded.
After the upload is complete, click Close.
After the deployment starts, the M2000 deploys only the NodeB.
For details about the automatic commissioning performed by the M2000, see
Commissioning of the MBTS on the
Task.
The M2000 client is started.
MBTS commissioning preparations are complete.
The controller to which the MBTS to be commissioned belongs is properly connected to
the M2000.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3900 Series Multi-Mode Base Station
M2000.
4.6.1 Viewing the Progress and Status of an MBTS
Commissioning Guide
on the toolbar. The
4.5 Automatic
Issue 02 (2010-07-30)

Hide quick links:

Advertisement

Table of Contents