Viewing The Service Verification Results Of An Mbts; Table 4-6 Procedure Of Automatic Service Verification - Huawei 3900 Series Commissioning Manual

Multi-mode base station
Hide thumbs Also See for 3900 Series:
Table of Contents

Advertisement

4 Commissioning the MBTS in GU Mode on the M2000

4.6.4 Viewing the Service Verification Results of an MBTS

This section describes how to view the service verification results of an MBTS. After the
automatic service verification starts, the M2000 automatically collects the performance data
related to the GBTS and NodeB services and checks whether the services are normal.
Prerequisite
The automatic software commissioning already starts, and you have not confirmed the
completion of the commissioning yet.
Context
For details about the process of MBTS service verification, see
service verification window, see

Table 4-6 Procedure of automatic service verification

Step
1. The M2000
collects the
performance data
related to the
GBTS and
NodeB services.
4-20
Interface Description: Commissioning the
Description
If you do not restart the MBTS
commissioning or confirm the completion
of the commissioning after the service
verification starts, the M2000 collects the
performance counter data related to the
GBTS and NodeB services according to the
shortest measurement period currently
supported by the NEs.
The performance counters of an MBTS
consist of the performance counters of the
GBTS and the performance counters of the
NodeB. For details, see
for MBTS Service Verification
Performance
Counters.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3900 Series Multi-Mode Base Station
Table
Operation Performed
by Users
Not involved.
4.9.3 Parameters
Commissioning Guide
4-6. For details about the
MBTS.