Table 5-2 Item List Of The Nodeb Commissioning Procedure - Huawei 3900 Series Commissioning Manual

Multi-mode base station
Hide thumbs Also See for 3900 Series:
Table of Contents

Advertisement

3900 Series Multi-Mode Base Station
Commissioning Guide

Table 5-2 Item list of the NodeB commissioning procedure

Commissionin
g Item
Detecting the
OM channel
Upgrading the
software and
configuration
Monitoring the
software
commissioning
Verifying the
services
Completing the
NodeB
deployment
Issue 02 (2010-07-30)
Description
When the transmission network is functional, the M2000 automatically
sets up the OM channel with the NodeB according to the NodeB
deployment list. The OM channel is used to commission and maintain the
NodeB.
After the OM channel is set up, the M2000 automatically sets Special
Status of the NodeB to Testing, so that the invalid alarms can be shielded
during commissioning.
According to the version information in the NodeB deployment list, the
M2000 automatically checks whether the current NodeB version is the
same as the target version. If the current NodeB version differs from the
target software version, the target software and data configuration file are
downloaded from the server to the NodeB and activated automatically.
NOTE
If the USB disk is used for the upgrade on the NodeB side, and the NodeB software
and data configuration file are upgraded to the target version, the M2000 skips this
step and proceeds with the automatic software commissioning.
The purpose of software commissioning is to verify the services. Software
commissioning starts automatically. During the commissioning, only
faults need to be noted. All the reported alarms are displayed on the
monitoring interface of the M2000. In addition, the fault diagnosis access
that facilitates quick fault location is available, and the associated handling
suggestions are provided.
When detecting that the logical cell of the NodeB is available, the
M2000 starts service verification. The M2000 determines whether service
verification succeeds according to key performance counters, and then
displays the results.
After a NodeB passes the service verification, the status of the
commissioning task changes to Waiting for Acknowledgement. When
the user acknowledges the completion of commissioning tasks, the
M2000 automatically cancels the Testing state of the NodeB and verifies
the NodeB location.
NOTE
Cancel the Testing state of the NodeB and resume the alarm reporting of the
l
NodeB.
NodeB location verification refers to the process in which the M2000
l
automatically checks whether the ESN reported by the NodeB is the same as the
ESN in the NodeB deployment list. Through the NodeB location verification,
you can check whether the USB disk for upgrade is the correct one in IP
networking mode.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Commissioning the MBTS in GL or UL Mode on the
M2000
5-23