96 Installation checklist
Check that ....
There is an adequately sized protective earth (ground) conductor between the drive and the switchboard.
There is an adequately sized protective earth (ground) conductor between the motor and the drive.
All protective earth (ground) conductors have been connected to the appropriate terminals and the
terminals have been tightened (pull conductors to check).
The supply voltage matches the nominal input voltage of the drive. Check the type designation label.
The input power cable has been connected to appropriate terminals, the phase order is, and the ter-
minals have been tightened. (Pull conductors to check.)
Appropriate supply fuses and disconnector have been installed.
The motor cable has been connected to appropriate terminals, the phase order is right, and the terminals
have been tightened. (Pull conductors to check.)
The motor cable has been routed away from other cables.
The control cables (if any) have been connected to the control board.
If a drive bypass connection will be used: The direct-on-line contactor of the motor and the drive output
contactor are either mechanically or electrically interlocked (cannot be closed simultaneously).
There are no tools, foreign objects or dust from drilling inside the drive.
Drive and motor connection box covers are in place.
The motor and the driven equipment are ready for start-up.