18 Introduction to the manual

Quick installation and commissioning flowchart

Task
Identify the frame of your drive: R0...R8.
Plan the installation: select the cables, etc.
Check the ambient conditions, ratings and required cooling air flow.
Unpack and check the drive.
If the drive will be connected to an IT (ungrounded) system, check that the
internal EMC filter and ground-to-phase varistor are not connected. If the
drive will be connected to a corner-grounded TN system, check that the in-
ternal EMC filter is not connected.
Install the drive on a wall.
Route the cables.
Check the insulation of the input cable and the motor and the motor cable.
Connect the power cables.
Connect the control cables.
Check the installation.
See
Type designation la-
bel (page 33)
Planning the electrical installa-
tion (page 49)
Introduction to the manu-
al (page 17)
Mechanical installation:
Unpack-
ing and examining delivery,
frames R0...R2 (page
39),
packing and examining delivery,
frames R3...R4 (page
40),
packing and examining delivery,
frames R5 (page
41),
Unpacking
and examining delivery, frames
R6...R8 (page
42).
Operation principle and hard-
ware description:
Type designa-
tion label (page 33)
Electrical installation:
Checking
the compatibility with IT (un-
grounded) and corner-grounded
TN systems (page 63)
Mechanical installa-
tion (page 37)
Planning the electrical installa-
tion:
(page 54)
Electrical installation:
Checking
the insulation of the as-
sembly (page 61)
Electrical installation:
Connect-
ing the power cables (page 67)
Electrical installation:
Connect-
ing the control cables (page 80)
Installation checklist (page 95)
Un-
Un-