Figure A-7 Connecting the hose to the DPJ end connector
Step 5 Screw the ferrule into the plastic-coated metal hose, as shown in
Figure A-8 Installing a DPJ end connector
Step 6 Route the cable into the pre-fab. module through the body of the DPJ end
connector.
● People inside and outside the pre-fab. module should work together to route
the cable to the specified connection position inside the pre-fab. module.
● To facilitate operation during internal routing, you can remove some top plate
in the pre-fab. module aisle.
Step 7 Connect the ferrule to the body and tighten the cover lock nut using the dedicated
feeder window wrench.
Step 8 Apply sealant on the joint between the DPJ end connector and the sheet metal on
the pre-fab. module, as shown in
Figure A-9 Applying sealant
Step 9 Spray water to test the waterproof performance of the DPJ end connector.
----End
Issue 07 (2022-12-15)
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
A Basic Installation Operations
Figure
A-9.
Figure
A-8.
115

Advertisement

Table of Contents
loading

Table of Contents