Figure 9-1 Installing mounting ears
Step 3 Push the battery pack onto the guide rails, and secure the battery pack to the
cabinet rack rails using mounting ears and screws.
Figure 9-2 Installing a battery pack
Step 4 Install other battery packs in the same way.
Step 5 Connect cables between battery packs based on the battery pack wiring diagram.
----End
Follow-up Procedure
Verify the battery pack cable connections. Ensure that the battery pack quantity
and cable connections comply with the design and the cables or copper bars are
reliably installed.