Step 1 Select a cable to be connected between two devices. Measure the cable route
length between the two devices using a thin rope or small cable (such as a signal
cable or fire control cable) available on-site.
Step 2 Add the length reserved for installing terminals and a tolerance to the cable
length measured in
----End
A.1.3 Laying Out Cables
Prerequisites
Some external cables for the FusionModule1000 are long and thick. Assign at least
two persons to lay out cables especially armored cables if no assistant tool is
available onsite.
Preparations
Tools: protective gloves and marker
Material: cable
Document: none
Skill requirement: common technician
Procedure
Step 1 Select the designed cables.
Step 2 Lay out cables to the required run length.
Issue 07 (2022-12-15)
Step 1
NO TE
● To improve installation efficiency, complete all cable measurements before you perform
subsequent operations.
● Determine the length of the other cables between the devices based on the length of
the cable measured.
● To facilitate installation, it is recommended that you lay out cables to the measured
cable route length plus about 2 m.
Do not lay out cables outdoors under bad weather conditions if no shelter is
available.
Cables have been measured.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
to determine the required cable run length.